Seven Gates Indonesia
Past Project

Chandra Asri Alkali & Krakatau Chandra Energi

Additional Work Land Preparation & Land Preparation KCE
Project area

Approximately 15 Ha

Located in

Cilegon, Banten

Filling volume

Approximately 270,000 m³

Working period

23 Nov 2024 – 19 June 2025

Scope of works

Clearing, Stripping, Dewatering, Sand Filling & Compaction

Executed for PT Chandra Asri Alkali and Krakatau Chandra Energi in Cilegon, Banten. The project covers an area of approximately 15 hectares and a filling material volume of around 270,000 cubic metres. The scope includes site clearing, site stripping, dewatering, sand filling, and heavy compaction, running from 23 November 2024 to 19 June 2025.